February 15, 2021
Construction Update February 2021
February marks one year of non-stop construction on-site! These two weeks were a little less busy with movement, as we prepare for the next construction phase of City Center West Orange Phase 1 buildings. But we still had continual progress on-site! Additional foundation boxes were built for the main Phase 1 building. Concrete was poured into those foundation boxes. Site clean-up continued and dirt was brought to foundations to fill-in sides.